If the budget is enabled at the line level, you can allocate different budgets for each line in a single purchase order (PO), allowing you to distribute the cost across multiple budgets.

Step-by-Step Instructions

Step 1: Go to Configurations

  • Log in and navigate to the admin console.

  • Select the "Configurations" option from the menu.

Step 2: Click on Company Settings

  • Navigate to "Company Settings."

Step 3: Enable Budget at Line Level

  • Under the "General" section, scroll down to find the "Enable Budget" option.

  • Choose the option to enable the budget at the line level.

Step 4: Save the Settings
Click "Save" to apply the changes.

Once these steps are completed, you can select different budgets for each line in a PO.